Home / Schemes/Projects / Design Tool-8 (version 2) – Cost Estimate of a Water Supply Scheme

Design Tool-8 (version 2) – Cost Estimate of a Water Supply Scheme Last Updated : Sat, 21 Nov 2026

JSV Design Tool-8 (version 2) – Cost Estimate of a Water Supply Scheme – Himachal Pradesh

Design Tool-8 (version 2) – Cost Estimate of a Water Supply Scheme – Jal Shakti Vibhag, Himachal Pradesh

Follows the JSV "Analysis of Rate" method: lead-wise carriage (truck table and head-load table), material, labour and sundries, water charges, contractor's profit (10 % except cement / steel), overheads (5 %), GST and labour cess in the item rate; flanged-pipe, valve and chamber analyses; a dated basic-rate sheet. Prices all components of Tools 1 to 7, including lump-sum items that need subjective evaluation.

I1. Location, rate-year stamps, JSV add-ons (profit, overheads, GST, cess) and SoR override
I2. Basic-rate sheet (materials, labour, fuel, pipes, valves) – dated, with paste / save / load
I3. Leads and carriage (truck table and head-load table)
I4. Hydraulics (CPHEEO) – population, LPCD, pumping stages, static lift (Tools 1, 4, 6)
I5. Civil – strata, source and intake, sump well, raw-water tank, WTP, tanks, pump houses (Tools 1, 2, 3, 5)
I6. Pipes, valves, E&M, distribution, house connections, automation and IoT (Tools 4, 5, 6)
I7. Financial and tender – escalation, contingencies, centage, O&M
I8. ESHS, gender, OHS, QA/QC drivers and lump-sum (subjective) provisions (Tool-7 and all tools)
Planning-stage estimating aid for departmental use. Coefficients and rates marked W follow the JSV Analysis of Rate workbook; those marked A are assumptions that the workbook does not cover (HDPE pipe, E&M, IoT, WTP equipment and similar) and must be replaced by quotations or SoR rates; L marks lump sums that need the engineer's judgement; S marks rates pasted from a Schedule of Rates. The tool does not contain the notified Schedules of Rates. Statutory charges (GST, BOCW cess, centage) and HPSEBL rules must be checked against current orders. The estimate is a draft for the competent officer to review, adapt and sign.